APG QC#
Description
Q1
INSPECTION SYSTEM REQUIREMENT
The supplier shall have in place a system/program that conforms to (as applicable): Quality system / Program Requirements MIL-I-45208, AS9100 or ISO-9001
Q2
CALIBRATION SYSTEM
The supplier shall maintain a calibration system that is in compliance with ANSI/NCSL Z 540-3 or ISO 17025 (latest revision). Calibration records shall show traceability of the standards used for calibration to the National Institute of Standards and Technology (NIST) or other nationally recognized calibration standards.
Q3
PART/LOT
TRACEABILITY/SERIALIZATION
Requirement that all parts have unique serial numbers maintained and/or assigned. Maintain S/N traceability at all stages of manufacturing or processing. Indicate S/N's on all certifications, inspection reports, shipping documents and/or other documentation as applicable.
Q4
FIRST ARTICLE INSPECTION FULL AS9102
A complete First Article Inspection in accordance with the requirements of AS9102 is required. This first article will consist of one piece. This piece must be identified and packaged separately along with the report when shipped with the production parts.
Q5
FIRST ARTICLE INSPECTION AS9102 FORM 3 ONLY
A completed copy of an AS9102 Form 3 or equivalent must accompany each item specified on the purchase order. First article part must be identified and packaged separately.
Q6
100% INSPECTION REQUIRED
The supplier shall perform a 100% inspection of each part. A record of the inspection results shall be provided to APG, sampling inspection is not allowed.
Q7
APG SOURCE INSPECTION
APG source inspection is required. Inspection shall be conducted at the Seller's facility and shall be requested and accomplished prior to shipment. When the items on the Purchase Order are ready for inspection, notify the APG purchasing representative so that coverage can be arranged. Drawings, specifications and/or other pertinent data as required by the Purchase Order shall be made available to the APG Quality Representative, at the time of product presentation.
Q8
CERTIFICATION OF COMPLIANCE
Each shipment shall be accompanied by a dated certification signed by a responsible representative of the supplier, stating that the items were processed in conformance with the purchase order requirements, engineering drawing, revision and specification requirements including as a minimum the supplier name, purchase order, number, part number, quantities accepted and rejected. Additional quality requirements apply when referenced on the purchase order.
Q9
MATERIAL CERTIFIED PHYSICAL&CHEMICAL TEST REPORTS
Seller shall supply one copy of mechanical and/or chemical test reports for each lot, batch or heat, whichever is applicable. Seller shall supply original mill certification with shipment of material specified on the purchase order. The report must show that material/parts delivered are acceptable and identifiable to the product being delivered. The heat number and material manufacturer must appear on the certification. All metal alloys shall require traceability to the original heat number, and shall comply with the current material specification revision in effect when melted (or at time of contract award). The heat number and material manufacturer must appear on the certification. Material converters are responsible for maintaining heat lot traceability and are prohibited from welding, brazing, or otherwise joining coils.
Q10
PREFERENCE FOR DOMESTIC SPECIALTY METALS
In the performance of this contract and shall be flowed to suppliers at all tiers when parts, components, and or end item deliverables contain specialty metals. Use of specialty metals shall be confined only to those that have been smelted (the Deviation clause adds “or produced”) in the United States, its outlying areas, or a qualifying country listed in DFARS 252.225 http://www.acq.osd.mil/dpap/dars/dfars/pdf/r20121231/252225.pdf Note: Titanium is a specialty metal. Stainless Steel is a specialty metal because of its nickel content. DFARS 252.225-7008 and DFARS 252.225-7009, Restriction on Acquisition of Certain Articles Containing Specialty Metals (excluding Paragraph (d) which is deleted from this clause)(applicable to Purchase Orders under prime contracts awarded after July 28, 2009) DFARS 252.225-7010, Commercial Derivative Military Article—Specialty Metals Compliance Certificate (applicable to Purchase Orders under prime contracts awarded after July 28, 2009)
Exemptions to the requirements of the above clauses may exist, as outlined in the clauses themselves or by operation of applicable Department of Defense (DOD) Domestic Non-Availability Determinations (DNADs) posted on the DOD public web site. Contact the APG buyer if exemptions might apply
Q11
SPECIAL PROCESS CERTIFICATION
Any special processing performed on the material/parts associated with this purchase order shall
be individually certified. Certification shall include related data such as thickness, temperatures, and hardness results. These processes shall include but are not limited to heat treat, plating, paint, welding, NDT, etc.
Q12
PRESERVATION/PACKAGING
Packaging and Protection of the product shipped shall be in accordance with APG’s purchase order or best practice to protect product from damage and/or deterioration.
Q13
RIGHT OF ENTRY
The APG and APG’s customer, and their customers, or any applicable agency will have the right to enter the seller’s facility to perform inspection or ensure compliance to the contract.
Q14
IDENTIFICATION
Parts and/or material provided for this purchase order shall be identified with the part number, revision, and CAGE Code in accordance with MIL-STD-130 and/or drawing/specification requirements.
Q15
SPECIAL PROCESS APPROVAL FLOWDOWN
Supplier shall be responsible for using APG, APG's customer’s, and/or Government approved sources for the performance of special processing. Contact the buyer for names of the approved suppliers.
Q16
APPROVED SUPPLIER
All items supplied on this purchase order shall be purchased from only those suppliers approved by APG, APG's customer, and/or the Government. Contact APG for a list of approved suppliers.
Q17
BOEING APPROVED PROCESSOR
All processing on this purchase order shall be in accordance with D1-4426 (latest revision)
Boeing approved processors.
Q18
GRAIN DIRECTION
Grain Direction identification is required on this order. All pieces of raw stock shall be identified with an arrow or other means denoting the grain direction. Failure to identify grain direction shall be cause for rejection.
Q19
PROPER REVISION LEVEL
The supplier shall use the latest specification revision as called for in the purchase order. If the purchase order does not contain specification revisions, then revisions shall be per the latest industry standard.
Q20
BOEING D6-82479, AS9100, OR DI-9000 FLOWDOWN
The supplier is required to be BOEING approved to D6-82479, AS9100, or D1- 9000 (latest revision) for Basic Quality System Requirements for work performed on this purchase order. Proof of approval is required.
Q21
CAD/CAM DPD, MBD QUALITY SYSTEM FLOWDOWN QUALITY SYSTEM FLOWDOWN
Supplier is required to be BOEING approved to D6-51991 (latest revision), CAD/CAM Quality Assurance System Requirements, for work performed on this contract. Proof of approval is required.
Q22
NON-CONFORMING MATERIAL (PRODUCT)
The supplier shall notify APG of nonconforming products as soon as discovered by the supplier. Authority to ship discrepant material shall be obtained by the seller prior to shipment. Discrepant material shipped without prior approval MAY be rejected and returned at the seller's expense.
Q23
SUBCONTRACTING BY SUPPLIER
The supplier shall not subcontract any part of the manufacturing process or finishing process of any part on this order without prior written approval from APG. Supplier is also responsible to ensure flow down ALL of APG’s purchase order requirements to any and all sub-tier suppliers.
Q24
UNAUTHORIZED CHANGES
Seller must and shall not make any changes to the processes or materials specified under the purchase order. Seller shall notify APG in writing prior to any proposed changes to supplier controlled design, parts, materials, fabrication methods or processes, that may affect function, interchangeability or reliability of hardware delivered to APG or of any changes to facility location, ownership or quality management following a quality survey /audit by APG.
Q25
FOREIGN OBJECT DEBRIS (FOD) PROGRAM
Seller shall maintain a FOD prevention program. Seller’s FOD prevention program shall include the review of design and manufacturing processes to identify and eliminate foreign object entrapment areas and paths through which foreign objects can migrate. Seller shall ensure work is accomplished in a manner preventing foreign objects or material in deliverable items. Seller shall maintain work areas and control tools, parts and materials in a manner sufficient to preclude the risk of FOD incidents. Seller shall document and investigate each FOD incident and ensure elimination of the root cause of each incident.
Q26
SUPPLIER CORRECTIVE ACTION
When requested in writing by APG seller shall provide proof of corrective action, root cause and root cause corrective action for any deficiencies deemed supplier responsibility on Corrective Action Request. Failure to respond in a timely and/or effective manner may result in future on-site review, source inspection at supplier’s facility, being placed on purchase order hold status and/or removal from the APG Approved Supplier List.
Q27
RECORD RETENTION
All documentation (e.g., inspection records, contracts, purchase orders, process and material certifications, test reports, nonconforming material records) for materials supplied and or processed to APG shall be retained at the supplier for a minimum of TEN (10) years after the last delivery, and are not to be destroyed unless written approval is first obtained from APG. The supplier shall assure that all documentation is readily retrievable and available for review by APG, its customers or regulatory authorities as directed by APG. APG shall maintain the right, at any time whether before or after completion of the contract, to direct delivery of all or any portion of the documentation on either a permanent or temporary basis.
Q28
WRITE-IN REQUIREMENT
Any requirements not specified above shall be explained in detail here or in an accompanying document.
Q29
APG FURNISHED DOCUMENTS/DATA/TOOLING
All DRAWINGS, DOCUMENTS, MYLARS, TOOLING AND RELATED DATA are to be returned to APG upon completion of the PO or Contract.
Q30
ITAR REQUIREMENT
Supplier/Seller shall comply with International Traffic in Arms Regulation §122.1, Registration requirements.
Q31
PROCESS CHANGE CONTROL
Amendments to this purchase order, or APG’s terms and conditions shall be set forth in writing, via purchase order change notice, and/or revisions to the purchase order terms and conditions. APG will consider seller’s request to modification of, or exception to, only if such request is made in writing, prior to the acceptance of the order (ref: acceptance clause).
Q32
COUNTERFEIT PARTS PROGRAM (GIDEP)
Applicable if eligible
Q33
Conformity, Product Safety, and Ethical Behavior
The supplier shall ensure that all personnel assigned to this project are aware of:
- their contribution to product or service conformity;
- their contribution to product safety;
- the importance of ethical behavior.
REV B 04/10/19
Copyright © 2021 American Precision Group - All Rights Reserved.
We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.